These sites were subjected to physical verification, following which: A practical reader guide

2026, local bodies can levy user fees on waste generators: A practical reader guide

The Haryana State Pollution Control Board (HSPCB) has recommended the closure of 34 construction sites in Gurugram for failing to comply with CAQM-mandated air-pollution monitoring and dust-mitigation requirements, officials said on Monday.

CAQM’s 2024-25 report, released in December 2025, said its enforcement mechanism included remote monitoring of larger C&D projects and action against grossly violating sites, including closure directions.

Over 400 construction and demolition (C&D) sites in southern Gurugram were issued show-cause notices on September 10 after virtual verification found lapses in mandatory monitoring systems, including missing pan-tilt-zoom (PTZ) cameras, non-functional air-quality sensors, broken live feeds and inadequate camera coverage, according to officials. Officials said around 350 sites subsequently complied with the requirements, while around 50 remained non-compliant after the September 17 deadline. These sites were subjected to physical verification, following which 34 were recommended for closure.

The final decision will be taken at the HSPCB headquarters level.

“Project proponents were given a window of five to seven days to operationalise the cameras, ensure continuous live streaming to the central portal, and provide compliance reports, but these 34 sites have failed to do so,” a senior HSPCB official told HT.

In September, HSPCB summoned around 170 project representatives to review the functioning of web cameras, self-audit reports and fortnightly compliance certifications.

The board said inspections would also examine dust screens, wind barriers, sprinklers and other mitigation measures.

The latest action is part of a wider push to improve monitoring of dust-generating activities before the winter pollution season.